Service Reservoir

Posted on: 1st Jun 2008 by: WLS: Water-Lines Solutions Ltd

Client

Stonbury

Project Objective

Relining of a potable water reservoir.

Description

The reservoir had been lined with a rubber membrane which had deteriorated and was starting to leak. Approximately 6,000m² of DWI approved flexible membrane was installed to a height of 3.3m from the floor including 183 square columns resting on circular plinths.

Pipeworks entering the reservoir were sealed with a DWI liquid applied system.

The Project required multiple-trained welding technicians working for 8 weeks below ground in a process which included regular calibration of machinery and air testing to welded joints. The Project, once completed, was placed on a 2 week drop test and then put back into service.

Products involved

DWI approved flexible membrane.

Outcome

Reservoir successfully brought back into service.

Benefits

Flexible membrane can be installed relatively quickly without numerous repairs to existing structure.

Date

June 2008

Think we can help?

Simply leave your details below and one our our team will contact you.


#BaffleCurtain installation by Water-Lines Solutions. Check out our website http://www.water-lines.co.uk for more inform… https://twitter.com/i/web/status/1070990841387327488

6 days ago

Another successful #bafflecurtain installation. https://t.co/wPpIG1hCNz

3 months ago

#bafflecurtain installation by our technicians, looking good guys, well done!! https://t.co/3sGn3pYF2B

5 months ago

The sun is shining and our technicians are busy installing #totalgasbarrier in Nottingham. If you would like to enq… https://twitter.com/i/web/status/996032976914960384

6 months ago